Plainfield HS Site Visit Report: 12/22/2023
Visit Date: December 22, 2023
Members On-Site Include:
- Bob Kress – Northeast Stage
- Victor Fontana – Service Division Manager @ Sal Electric
- Andy Hulse – A/V Engineer @ PureTek Group
- Mike Litvin – COO @ PureTek Group
Overview:
- Work is proceeding rapidly in the Esports arena:
- The walls have been painted black and windows treated.
- The half walls for the desks have been completed and painted.
- Equipment is being mounted including the TV mounts, PTZ cameras, moving lights, and more.
- Rigging repairs are being conducted in the auditorium including changing out the old arbors to repair the counterweight fly system.
- The existing curtains are being taken down in the auditorium. Plainfield Public Schools can repurpose these for another location or dispose of them.
What’s Next?
- PureTek engineering determined the IMAX screen delivered included a non-compatible mounting mechanism. An RMA is being conducted that will swap out the delivered screen with a new, compatible screen. PureTek team member, Andy Hulse, will coordinate with the Plainfield HS team to coordinate screen pickup.
- Work will continue in the Esports arena including the mounting of lights and more technology.
- The teams are working together to make small adjustments to the pipe grid in the Esports arena to ensure a high-end and incredibly aesthetically pleasing design. We all want this space to look amazing.