Visit Date: August 28, 2024

Overview:

  • Auditorium
    • Completed the of pre-wiring walk-through.
    • A plan of action has been determined.
    • Demo work was started. 4 foot Iures under the balcony have been removed.
    • Demo work will continue with the fixtures on the ceiling tomorrow morning
    • Inventory of everything on site was performed, boxes were separated by category
    • The projection screen was delivered and received by the PureTek Team

What’s Next?

  • Scaffolding to be setup on stage to allow for over-stage demo, rigging, and electrical work.
  • House lighting installation to initiate early next week.
  • Materials will continue to be delivered on site.

Visual Updates