Visit Date: August 28, 2024
Overview:
- Auditorium
- Completed the of pre-wiring walk-through.
- A plan of action has been determined.
- Demo work was started. 4 foot Iures under the balcony have been removed.
- Demo work will continue with the fixtures on the ceiling tomorrow morning
- Inventory of everything on site was performed, boxes were separated by category
- The projection screen was delivered and received by the PureTek Team
What’s Next?
- Scaffolding to be setup on stage to allow for over-stage demo, rigging, and electrical work.
- House lighting installation to initiate early next week.
- Materials will continue to be delivered on site.