Plainfield HS Site Visit Report: 4/11/2024
Visit Date: April 11, 2024
Overview:
- Esports
- As seen in the images below, Esports lighting, audio, visual, and broadcasting technologies are installed. The PureTek team is continuing tech setup, testing, and programming.
- Manufacturer programmers will be setting up the presets in this space during the week of 4/15 – 4/19.
- Auditorium
- Installation of the seating and carpeting is in progress.
- The IMAX screen has been installed.
- FOH motor installation scheduled for next week.
- Replacement roll-top desk scheduled for shipment on April 12.
- Manufacturer programmers will be setting up the presets in this space during the week of 4/15 – 4/19.
- Black Box Theater
- Rack setup scheduled to commence next week
- Lighting, projector, and screen installation completed.
- Seating and flooring completed
What’s Next?
- Auditorium: Finalize seating installation and continue programming the lighting system in the Auditorium.
- Esports Room: Wrap up tech setup and conduct additional testing for the Esports area.
- Blackbox Theatre: Build out the rack and putting the finishing touches on audio-video components and lighting.