Plainfield HS Site Visit Report: 4/18/2024

Visit Date: April 18, 2024

Overview:

  • Esports
    • ETC Paradigm systems are now fully operational, seamlessly integrated with the E-Sports area
    • Madrix programming is complete, offering versatile presets and easy customization for dynamic lighting effects.
    • Inverters and EM transfer switches have been repaired and are undergoing final testing.
  • Auditorium
    • The ETC Mosaic system is fully functional, providing precise control over lighting with impressive precision.
    • Currently developing engaging presets for Madrix and coordinating with IT personnel for theater presets.
    • Addressed minor issues with Acolyte LED strip installation to ensure optimal performance.
  • Black Box Theater  
    • ETC Paradigm systems are now operational, seamlessly integrated into the Blackbox area.
    • Madrix programming is finalized, offering flexible presets and simple customization for dynamic lighting effects.
    • Inverters and EM transfer switches have been repaired and tested to ensure reliable functionality.

    What’s Next?

    • Auditorium: Installation of goof rings for orchestra pit trims, completion of FOH hoist repairs, patching of FOH hoist hole, completion of seating installation, completion of carpet installation, and installation of aisle lighting.
    • Esports Room: On-site Crestron integration, space clean up, and training.
    • Blackbox Theatre: Build out the rack and putting the finishing touches on audio-video components and lighting.

    Visual Updates

    April 18, 2024