Plainfield HS Site Visit Report: 4/11/2024

Visit Date: April 11, 2024

Overview:

  • Esports
    • As seen in the images below, Esports lighting, audio, visual, and broadcasting technologies are installed.  The PureTek team is continuing tech setup, testing, and programming.
    • Manufacturer programmers will be setting up the presets in this space during the week of 4/15 – 4/19.
  • Auditorium
    • Installation of the seating and carpeting is in progress.
    • The IMAX screen has been installed.
    • FOH motor installation scheduled for next week.
    • Replacement roll-top desk scheduled for shipment on April 12.
    • Manufacturer programmers will be setting up the presets in this space during the week of 4/15 – 4/19.
  • Black Box Theater  
    • Rack setup scheduled to commence next week
    • Lighting, projector, and screen installation completed.
    • Seating and flooring completed

    What’s Next?

    • Auditorium: Finalize seating installation and continue programming the lighting system in the Auditorium.
    • Esports Room: Wrap up tech setup and conduct additional testing for the Esports area.
    • Blackbox Theatre: Build out the rack and putting the finishing touches on audio-video components and lighting.